Synth in Sync, Onsite in NSW

Recently InKorr (in collaboration with our partner Mersen) completed an Onsite project for a client in the Chemical manufacturing industry where we performed a complete strip-down refurbishment of a Hydrochloric Acid Synthesis Unit.
InKorr and the client worked together prior to the shutdown works preparing all the necessary staffing, a detailed plan of works from start to finish, required tools & equipment, replacement parts (Graphite components, gaskets & bolt sets) and contingency plans if any issues were to arise throughout the critical stages of works.


All components were disassembled and removed from their Skid, for detailed inspection, repair/refurbishment and replacement where required.
Due to the importance this piece of equipment holds in our clients production, InKorr were tasked with completing this project in as short a time as possible.
Performing back to back day and night shifts, and supervising a total of 20 people working together, the planning and preparations for this project proved well worth it.
A window of approximately 7 days was estimated to complete the job, which was achieved & bettered by almost a whole day!
Following the completion of the refurbishment works, the unit was tested via hydrostatic pressure test, even and level absorption water distribution & full operational testing. All of which passed with great success.
InKorr then assisted in the restart and commissioning of the unit back into service, followed by provision of a detailed service report, testing certificates along with recommendations for ongoing maintenance, future works and spare parts.

InKorr are proud to confirm, following a debrief and check up meeting with the client, that they are once again producing great quality product for their customers! We look forward to continuing our support with this client.